Tuesday, February 14, 2017

Internship in Nestlé - 13-14th Feb 2017 (8am - 5pm)

Monday, 13th Feb 2017 (8am - 5pm)

At 9.15 a.m., we had a daily review meeting with the operators.

At 9.45 a.m., I guided the WWTP operator, Vasu to recognize the new DPRS data log sheet in the control room. I told him to use this log sheet onwards for recording DPRS parameters.

Between 9.00 a.m. and 12.00 p.m., Jaclyn had asked me to prepare a guideline for basket strainer cleaning at the DPRS site. She explained the steps of cleaning to me. Later, I went to the site to take several photos to be inserted into the guideline for illustrations. I had emailed the guidelines to Tee and Jaclyn for checking once completed. Then, Tee reminded us to include LOTO practice during cleaning. It is important to apply LOTO for safety purposes.

Between 8.00 a.m. and 5.00 p.m., I continued to prepare the detailed SOP of the new DAF system. After that, I began to prepare another format (simple version) of SOP in flow chart. 


Tuesday, 14th Feb 2017 (8am - 5pm)

At 8.00 a.m., I did a final check on the SOP of the new DAF system before emailing this file to Tee. 

At 9.15 a.m., we had a daily review meeting with the operators as usual. 

At 10.00 a.m., I received an email about the information of the End Internship Presentation, which is scheduled for next Thursday morning. We should prepare a presentation slide about the projects involved.

Between 9.00 a.m. and 5.00 p.m., I was revising and updating the WWTP flow diagram, which was drawn during the early internship period. Meanwhile, Fam had followed up on the Spare Parts Lists, and Tee had informed me that we would have a short meeting to discuss the Spare Parts Lists and FLOCs.  